HP0753
LD 1060
Session - 126th Maine Legislature
 
LR 1120
Item 1
Bill Tracking, Additional Documents Chamber Status

An Act To Address Rising Electric Transmission Rates

Be it enacted by the People of the State of Maine as follows:

Sec. 1. 35-A MRSA §3132, sub-§2-C, ¶¶B and C,  as enacted by PL 2009, c. 309, §2, are amended to read:

B. Justification for adoption of the route selected, including comparison with alternative routes that are environmentally, technically and economically practical; and
C. Results of an investigation by an independent 3rd party selected by the commission of nontransmission alternatives to construction of the proposed transmission line including . These alternatives include energy conservation, demand response, distributed generation or and load management. The investigation must set forth the total projected costs of the transmission line as well as the projected costs of the alternatives, regardless of the proposed allocation of these costs by the New England independent system operator; and

Sec. 2. 35-A MRSA §3132, sub-§2-C, ¶D  is enacted to read:

D A description of the need for the proposed transmission line.

Sec. 3. 35-A MRSA §3132, sub-§§2-D and 2-E  are enacted to read:

2-D Lower-voltage projects requiring commission review and approval.   Whenever a person proposes to erect in the State a transmission line capable of operating at less than 69 kilovolts and projected to cost in excess of $20,000,000, that person must provide the commission the information set forth in subsection 2-C, paragraphs C and D.
2-E Standard for lower-voltage projects.   For a project the commission reviews under subsection 2-D, in order for the project to be approved, the commission must make a finding that the identified need cannot be economically and reliably met using nontransmission alternatives. During its review the commission shall give preference to nontransmission alternatives that have been identified as able to address the identified need at lower total cost. The commission shall give preference to the alternatives in the following order:
A Energy efficiency and demand response;
B Renewable distributed generation;
C Distributed generation with no greenhouse gas emissions; and
D Other distributed generation.

Sec. 4. 35-A MRSA §3132, sub-§5,  as enacted by PL 1987, c. 141, Pt. A, §6, is amended to read:

5. Commission approval of a proposed line.   The commission may approve or disapprove all or portions of a proposed transmission line and shall make such orders regarding its character, size, installation and maintenance as are necessary, having regard for any increased costs caused by the orders. The commission shall give preference to nontransmission alternatives that have been identified as able to address the identified need at lower total cost. The commission shall give preference to the alternatives in the following order: energy efficiency and demand response; renewable distributed generation; distributed generation with no greenhouse gas emissions; and other distributed generation.

Sec. 5. 35-A MRSA §3132, sub-§6,  as repealed and replaced by PL 2011, c. 281, §1, is amended to read:

6. Commission order; certificate of public convenience and necessity.   In its order, the commission shall make specific findings with regard to the public need for the proposed transmission line. The commission shall make specific findings with regard to the likelihood that nontransmission alternatives can address the identified public need at lower total cost. If the commission determines that the nontransmission alternatives can address the need at lower total cost but represent a larger increased cost to the ratepayers of the State than the proposed transmission line, the commission shall make reasonable efforts to achieve an agreement among the states within the New England independent system operator region to allocate the cost of the nontransmission alternatives among the ratepayers of the region using the allocation method used for transmission lines or another allocation method that results in lower increased cost to the ratepayers of the State. Except as provided in subsection 6-A for a high-impact electric transmission line, if the commission finds that a public need exists and that the need cannot be economically and reliably met using nontransmission alternatives, it shall issue a certificate of public convenience and necessity for the transmission line. In determining public need, the commission shall, at a minimum, take into account economics, reliability, public health and safety, scenic, historic and recreational values, state renewable energy generation goals, the proximity of the proposed transmission line to inhabited dwellings and alternatives to construction of the transmission line, including energy conservation, distributed generation or load management. The commission may not issue a certificate of public convenience and necessity for the transmission line unless all cost-effective energy efficiency and demand response resources are being acquired in the service territory of the utility or utilities through which the transmission line runs. If the commission orders or allows the erection of the transmission line, the order is subject to all other provisions of law and the right of any other agency to approve the transmission line. The commission shall, as necessary and in accordance with subsections 7 and 8, consider the findings of the Department of Environmental Protection under Title 38, chapter 3, subchapter 1, article 6, with respect to the proposed transmission line and any modifications ordered by the Department of Environmental Protection to lessen the impact of the proposed transmission line on the environment. A person may submit a petition for and obtain approval of a proposed transmission line under this section before applying for approval under municipal ordinances adopted pursuant to Title 30-A, Part 2, Subpart 6-A; and Title 38, section 438-A and, except as provided in subsection 4, before identifying a specific route or route options for the proposed transmission line. Except as provided in subsection 4, the commission may not consider the petition insufficient for failure to provide identification of a route or route options for the proposed transmission line. The issuance of a certificate of public convenience and necessity establishes that, as of the date of issuance of the certificate, the decision by the person to erect or construct was prudent. At the time of its issuance of a certificate of public convenience and necessity, the commission shall send to each municipality through which a proposed corridor or corridors for a transmission line extends a separate notice that the issuance of the certificate does not override, supersede or otherwise affect municipal authority to regulate the siting of the proposed transmission line. The commission may deny a certificate of public convenience and necessity for a transmission line upon a finding that the transmission line is reasonably likely to adversely affect any transmission and distribution utility or its customers.

summary

This bill requires that the Public Utilities Commission may not issue a certificate of public convenience and necessity for the construction of a transmission line unless a description of the need for the proposed transmission line is provided; an analysis of nontransmission alternatives is conducted by an independent 3rd party selected by the Public Utilities Commission; the projected cost of the proposed transmission line is compared to the projected cost of feasible nontransmission alternatives based on total projected costs, regardless of who pays; preference is given to lower-cost alternatives; cleaner alternatives are given preference over alternatives that rely on fossil fuels; the Public Utilities Commission makes specific findings as to whether alternatives can address the identified need at lower total cost; and all cost-effective energy efficiency and demand response resources are being acquired in the applicable service territory of the utility that has proposed the project. This bill requires that, when the commission determines that the nontransmission alternatives can address the need at lower total cost but represent a larger increased cost to ratepayers of the State than the proposed transmission line, the commission make reasonable efforts to achieve an agreement among the states within the New England independent system operator region to allocate the cost of the nontransmission alternatives among the ratepayers of the region using the allocation method used for transmission lines or another allocation method that results in lower increased cost to ratepayers of the State.

This bill also requires that lower-voltage projects that are capable of operating at less than 69 kilovolts and projected to cost in excess of $20,000,000 must be reviewed and approved by the Public Utilities Commission before erection of the transmission line. The bill also establishes standards the Public Utilities Commission must use to review a lower-voltage project.


Top of Page