An Act To Streamline the General Permit Process for Tidal Power
Sec. 1. 38 MRSA §636-A, sub-§3, ¶D, as enacted by PL 2009, c. 270, Pt. D, §8, is amended to read:
Sec. 2. 38 MRSA §636-A, sub-§4, as enacted by PL 2009, c. 270, Pt. D, §8, is amended to read:
summary
This bill streamlines the permitting of a tidal energy demonstration project by the Department of Environmental Protection by specifying that the environmental assessment that includes a finding of "no significant environmental impact" is not required for the department to accept the application for processing. The bill establishes that the date of the notification of acceptance of the application for processing must be within 30 days of the filing of the assessment if it was not filed at the time of the initial application.